• Home
  • About the project
  • How to donate

This Old FIJI House

Not for college days alone…

Feeds:
Posts
Comments
« 2nd floor walls going up – finishes selected
Fire-rated windows arrive »

Finish work starts on the “old” side

June 2, 2011 by Eric

Tile floor has been installed in the 3rd old bathroom

Finish work started on the “old” side of the build – old is in quotes, because after this project is compete both the old, 1931 building, and the “new,” 1964 addition, will be virtually the same.

Tile work started in the 2nd and 3rd old bathrooms, ceilings are done and painters should move in next week to start painting walls on the 2nd, 3rd, and 4th floors of the old side of the chapter house.  Windows are also scheduled to be installed next week in the 1964 side of the building and the fire escape windows of the 1931 building.

The City of Lincoln will install a new water line to the building tomorrow for the fire sprinkler system.  The air conditioner compressor unit has arrived.  The 1964 chiller equipment was removed as part of this project. The old chiller has not worked for at least 20 years. The chiller room, located under the kitchen, will be used for storage.

Special thanks to Walter Gerlach (Nebraska 1958) for helping solve the mystery of the brass “More Phi Gam, Less Self” plaque that was found during demolition last February.  Brother Gerlach made two of these plaques (one for each door of the second and third floor bathroom) in the foundry located in the basement of Richards Hall.  One of the plaques has been mounted to an exterior column for the Undergraduate Brothers to see as they leave the house and to remind them of this fraternity creed. Thank you again Brother Gerlach for helping solve this mystery.

Windows will be installed next week on the 1964 addition.

Living room ceiling has been installed and will be finished next week.

Patch work will need to be done in the kitchen. Thankfully, the entire ceiling did not need to come down, just select areas to gain access to the heating system. The kitchen will also receive new appliances. If anyone wants to buy the old fridge (heck, if you want to get it out of there) drop the house corporation an email. It works fine, however, the bottom is starting to rust away.

Study area of room 200. The ceiling is done.

Room 210’s (formerly room 212) study area.  This room has two sleeping rooms of this shared area.

New windows in room 400 (formerly known as 4-North).

The study area of room 401 (formerly 4-South).  This is looking at the south wall of the chapter house.

Walls are going up in the new basement study room (formerly B1). The old stairs will blocked off.

All kinds of new pipes and pumps in the boiler room.

And, the new air condition compressor unit. This will be installed in the next few weeks.

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Related

Posted in 2nd new, 2nd old, 4th floor, history, kitchen, livingroom, mechanical systems, tile, windows |

  • Donation infomation

    Read how to support the project by clicking on the “How to Donate” tab at the top of the screen.
  • Enter your email address to subscribe to this blog and receive notifications of new posts by email.

    Join 40 other subscribers
  • This Old FIJI House archives

    • October 2011 (1)
    • August 2011 (4)
    • July 2011 (4)
    • June 2011 (5)
    • May 2011 (4)
    • April 2011 (4)
    • March 2011 (4)
    • February 2011 (6)
  • Recent Posts

    • The project is complete
    • FIJI is ready for business
    • They day before the fraternity property returns

Blog at WordPress.com.

WPThemes.


Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Follow Following
    • This Old FIJI House
    • Join 40 other followers
    • Already have a WordPress.com account? Log in now.
    • This Old FIJI House
    • Customize
    • Follow Following
    • Sign up
    • Log in
    • Copy shortlink
    • Report this content
    • View post in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...
 

    %d bloggers like this: