Archive for July, 2011

Updated 1st floor fire place and woodwork

New cement has been poured for the back lot and the DMZ. The original back lot was in disrepair, and the large trench that had to be dug to accommodate the new electrical service put the final nail in its coffin. While they were pouring the back lot, they also graded the DMZ and poured cement as well. This should solve the water issues for years to come.

Other finish works continues – including installing crown molding and baseboard in the living room, bathroom sinks, toilet dividers and tile work in the 1964 addition bathrooms. Painting and carpeting continues. The original 1931 wood floors are scheduled to be refurnished next week in the living room and tile installed in the kitchen and dining room.

Living room furniture has been ordered, 65 extra-long twin mattresses should arrive next week along with 90 window blinds. The next few weeks are going to be highly organized chaos, but the project is on schedule for an on time opening.

Living room trim work has been installed.

Foyer, looking from the dining room into the living room.

Dining room walls have been painted – ceiling is done.  Floors will be installed in the next two weeks.

2nd floor bathroom of the 1931 building — the sinks are located where the showers use to be.

2nd floor bathroom of the 1931 building — individual toilet stalls have been installed for privacy, shower curtain rods will added in the next week.

The study room for the new room 208 (old location of 208 and 209).  There are two bedrooms off this study room that will house two students each.

The 2nd floor hallway — going from the 1931 building to the 1964 addition.  A new door jamb has been installed for the balcony door.

New back lot!  The old surface needed to be replaced, but when the new power lines were buried, that sealed the deal.

The area between the ATO and FIJI house (known as the DMZ) has been paved.  This will help with basement water issues by getting water away from the building.

Phi Gamma Delta’s very own power transformer. The power lines are buried from the transformer to the house.

Read Full Post »

With less than a month before the project is scheduled to be complete, the finish crews have moved to the 1964 addition. Drywall has been hung, ceilings are up and bathrooms are ready for tile.  It will be a very busy month to meet the August 15 deadline.

Final finishes are in progress in the 1931 building – light fixtures, switches, plugs and plumbing fixtures are being installed. The house will have a new power service this week – which will allow us to fire-up the air conditioner for the first time to cool the property down.

In addition, the first shipment of dorm room furniture has arrived. Each sleeping room will have solid oak bunk beds, a dresser and wardrobe.  The study rooms will have a desk.  Living room furniture was ordered this week and will arrive August 16.

Stall dividers being installed in the 2nd floor bathroom of the 1931 building.

Drywall is up in the 1964 addition — this is the study area for 308 (formerly rooms 308 and 309).

2nd floor bathroom in the 1964 addition — tile work will begin next week.

Tile work in the housemother’s bathroom — new floor and fixtures are being installed.

Read Full Post »

The fire sprinkler main is open

Lots of progress this week – with dorm room furniture scheduled to be delivered on Friday, July 15 for the 1931 side.  The crews have been busy installing the fire sprinkler system (the item that started this entire project), HVAC equipment, carpet and paint.  Based on all known information at this point, the project is scheduled to be ready for the undergraduates to move in on August 15.

Inspections were approved to start finish work on the 1964 addition.  Drywall has been hung in the dining room, foyer, 2nd floor ceiling and 3rd floor.  Work continues on the bathroom.

The entire building will now enjoy central air.  The cooling equipment sits in the corner of the parking lot – where the ‘new’ and ‘old’ houses meet.  While this location is not ideal, it is the best solution that could be developed given the multiple factors that needed to be considered (including distance from the mechanical room and costs).  We were able to continue to use the boiler that was installed in 1997 for heat.

An individual ‘make-up’ air unit was installed for the kitchen.  This will provide both additional heat and air conditioning for this specific area of the chapter house.  The guys are going to have some cool cooks.   In addition, a new stove and refrigerator are on order for the kitchen.

The new AC has been installed on its pad.  While not ideal, this was the best of many not-so-good options.

Make-up air unit for the kitchen.  This will provide additional heating and cooling.

The living room has been primed with tinted primer.

The dining room has had drywall hung.

The housemother’s bedroom. Due to changes to the women’s restroom (will now be an ADA complain unisex restroom), the housemother’s bedroom gained much-needed, and I’m sure apprecaited, square footage.

Room 200 (formerly 200 and 201) carpet has been installed.  The camera continues not to do the actual colors justice.

Room 302 (formerly 303).

The 1964 addition has a little ways to go — this is taken in the study room of the new 309 (formerly 310 and 311), standing on the south wall — looking to the north.

The poor back lot took a beating and is scheduled to be paved next week.  The cement pad at the top of the photo is the location of the new transformer that will be installed next week as well.

Read Full Post »

Refinished dining room tables

The painters have finished 2nd, 3rd, and 4th floors of the 1931 building. The camera is not doing the colors justice – the hallways and individual sleeping rooms are light beige with the study rooms a light brown.  Carpet should be installed next week.

Mechanical and electrical rough-ins continue in the 1964 addition.  Fire sprinklers are being installed in the entire building.

Lincoln Electric System buried the power line last week.  While it is nice to have this line concealed, the downside is the back lot took a beating.  Luckily, as they dug a trench from the pole to the back of the 1931 building, no surprises were found (such as a buried fuel tank).

A new stove and refrigerator has been ordered to replace the 1964 appliances.  The fraternity’s freezer is relatively new and will be reused.

The board was able to contract with Cornhusker State Industries to custom build dorm room furniture (will be installed in the completed rooms next week).  CSI also refinished the dining room tables and a few other wood pieces from the chapter house.  The dining room tables look brand new and are ready for another 50 years of FIJIs celebrating lunch and dinner together.

Room 200 — the study room and sleeping room has been painted.

Room 401 (old 4 south) — the hallway that leads to the main study room. The sleeping rooms  are off to the right. 

The bathroom on the 1931 building — 3rd floor — ready for final finishes.

Mechanical and electrical rough-ins. Photo is taken on 2nd floor — looking west into room 210 (old 212 and cleaning closet).

3rd floor bathroom, 1964 addition — plumbing rough-ins are installed.  Drywall should start soon.

Fire sprinkler rough-ins on the 3rd floor, 1964 addition.

The 1964 appliances have been removed and new ones are on order.  The kitchen layout will remain relatively the same.

The poor back lot has seen better days — LES dug a trench from the pole in the middle of the photo to the back of the 1931 building to install a new power main.