The finishing touches are being put on the FIJI construction project. This week, rest of the carpet was installed on 2nd and 3rd floors, light fixtures are being hung in the building and various hardware is being installed (such as door handles, pulls, railing, etc). This weekend the cleaning crews move in to get the house ready for move in on August 18. The AC was fired up for the first time – and it appears to be working as expected.
New carpet on the ‘old’ stairs — from first floor. The railing is scheduled this week.
Living room – standing on the north wall – looking south to the fire place.
Living room — standing on the south wall — looking north (towards the front of the house)
Dining room floor has been installed and tables returned (they were refinished)
Detail of the new door hardware. The chapter house will have a master-key system — so the house corporation will have a single key that will open every door.
The new fire alarm panel — this is the extent of the exposed equipment.