Feeds:
Posts
Comments

Archive for the ‘3rd new’ Category

The final countdown

The finishing touches are being put on the FIJI construction project. This week, rest of the carpet was installed on 2nd and 3rd floors, light fixtures are being hung in the building and various hardware is being installed (such as door handles, pulls, railing, etc).  This weekend the cleaning crews move in to get the house ready for move in on August 18. The AC was fired up for the first time – and it appears to be working as expected.

Next week the construction crew will finish up and the chapter property, currently in storage, will be returned. If any graduate brothers in the Lincoln or Omaha area would like to come down on Tuesday, August 16 to help move our property back – please email the house corporation.
3rd floor hallway — between the 1964 and 1931 building. The doors to left are the location of the new laundry facility.  If you look all the way down the hall — you can see into room 310 (use to be 312).

New carpet on the ‘old’ stairs — from first floor.  The railing is scheduled this week.

Living room – standing on the north wall – looking south to the fire place.

Living room — standing on the south wall — looking north (towards the front of the house)

Dining room floor has been installed and tables returned (they were refinished)

Detail of the new door hardware.  The chapter house will have a master-key system — so the house corporation will have a single key that will open every door.

The new fire alarm panel — this is the extent of the exposed equipment.

Read Full Post »

Carpet, doors, and trim – the chapter house is starting to look like a home.  The next two weeks are going to be a flurry of activity to finish by August 17.  This week carpet is being installed in the hallways of the 1931 building and in the rooms of the 1964 addition.   The living room and housemother’s floors are being sanded and finished.

New solid core doors are being installed throughout the house.   A master-key system will be installed that will allow the house corporation to have a single key that will open all doors.  Each student’s key will unlock their study and assigned sleeping room door.

Next week’s highlights include firing up the air conditioner for the first time, installing the wireless internet system and rest of the finishes. FIJI is hosting all the UNL fraternity and sorority house corporations next week during the greek house tour.

If you haven’t done so already — mark your calendar and plan to attend Pig Dinner on Friday, October 7, 2011.  The chapter house dedication ceremony will take place on Friday at 4.30 p.m. with the 106th Norris Pig Dinner starting at 7. This year’s keynote address will be by the Honorable J. Robert Kerrey (Nebraska 1965), Former United States Senator and Governor of Nebraska.

Painting starts in the kitchen.  The kitchen will get a new stove and refrigerator.

The old ice room will house a new residential refrigerator, microwave and new ice machine.  Late plates and extra food will be stored in this room for guys to have access to in the evening.  The kitchen will remained locked when the cook is not present.

The 1964 stairwell has been painted and new railing installed.  Code requires new railings in both the 1964 and 1931 stairwells.

New hallway carpet in the 3rd floor of the 1931 building.

New doors have been installed.

The 3rd floor bathroom in the 1964 addition is ready for its final finishes.

New main electrical service panel — this feeds each of the subpanels on each floor.

All of the heating and cooling plumbing was redone.  The boiler room ceiling is almost fully covered in insulted pipes.

Read Full Post »

The fire sprinkler main is open

Lots of progress this week – with dorm room furniture scheduled to be delivered on Friday, July 15 for the 1931 side.  The crews have been busy installing the fire sprinkler system (the item that started this entire project), HVAC equipment, carpet and paint.  Based on all known information at this point, the project is scheduled to be ready for the undergraduates to move in on August 15.

Inspections were approved to start finish work on the 1964 addition.  Drywall has been hung in the dining room, foyer, 2nd floor ceiling and 3rd floor.  Work continues on the bathroom.

The entire building will now enjoy central air.  The cooling equipment sits in the corner of the parking lot – where the ‘new’ and ‘old’ houses meet.  While this location is not ideal, it is the best solution that could be developed given the multiple factors that needed to be considered (including distance from the mechanical room and costs).  We were able to continue to use the boiler that was installed in 1997 for heat.

An individual ‘make-up’ air unit was installed for the kitchen.  This will provide both additional heat and air conditioning for this specific area of the chapter house.  The guys are going to have some cool cooks.   In addition, a new stove and refrigerator are on order for the kitchen.

The new AC has been installed on its pad.  While not ideal, this was the best of many not-so-good options.

Make-up air unit for the kitchen.  This will provide additional heating and cooling.

The living room has been primed with tinted primer.

The dining room has had drywall hung.

The housemother’s bedroom. Due to changes to the women’s restroom (will now be an ADA complain unisex restroom), the housemother’s bedroom gained much-needed, and I’m sure apprecaited, square footage.

Room 200 (formerly 200 and 201) carpet has been installed.  The camera continues not to do the actual colors justice.

Room 302 (formerly 303).

The 1964 addition has a little ways to go — this is taken in the study room of the new 309 (formerly 310 and 311), standing on the south wall — looking to the north.

The poor back lot took a beating and is scheduled to be paved next week.  The cement pad at the top of the photo is the location of the new transformer that will be installed next week as well.

Read Full Post »

Refinished dining room tables

The painters have finished 2nd, 3rd, and 4th floors of the 1931 building. The camera is not doing the colors justice – the hallways and individual sleeping rooms are light beige with the study rooms a light brown.  Carpet should be installed next week.

Mechanical and electrical rough-ins continue in the 1964 addition.  Fire sprinklers are being installed in the entire building.

Lincoln Electric System buried the power line last week.  While it is nice to have this line concealed, the downside is the back lot took a beating.  Luckily, as they dug a trench from the pole to the back of the 1931 building, no surprises were found (such as a buried fuel tank).

A new stove and refrigerator has been ordered to replace the 1964 appliances.  The fraternity’s freezer is relatively new and will be reused.

The board was able to contract with Cornhusker State Industries to custom build dorm room furniture (will be installed in the completed rooms next week).  CSI also refinished the dining room tables and a few other wood pieces from the chapter house.  The dining room tables look brand new and are ready for another 50 years of FIJIs celebrating lunch and dinner together.

Room 200 — the study room and sleeping room has been painted.

Room 401 (old 4 south) — the hallway that leads to the main study room. The sleeping rooms  are off to the right. 

The bathroom on the 1931 building — 3rd floor — ready for final finishes.

Mechanical and electrical rough-ins. Photo is taken on 2nd floor — looking west into room 210 (old 212 and cleaning closet).

3rd floor bathroom, 1964 addition — plumbing rough-ins are installed.  Drywall should start soon.

Fire sprinkler rough-ins on the 3rd floor, 1964 addition.

The 1964 appliances have been removed and new ones are on order.  The kitchen layout will remain relatively the same.

The poor back lot has seen better days — LES dug a trench from the pole in the middle of the photo to the back of the 1931 building to install a new power main.

Read Full Post »

Framing on 3rd new

Wood studs and beams are being framed in on the 3rd floor of the 1964 addition. The original plan was to install cinder blocks, but the project engineer put a kibosh to that when the original manufacture of the floor joist system was not able to find records to confirm it the floor was designed to carry that kind of load. The modified plan calls for wood studs to be used, along with a handful of wood beams, to carry the load of the roof structure.

The heating and air conditioning work is being finished on the 1931 building.  For the first time, the entire building will be able to experience the joy of central air. Each room is equipped with its own fan coil unit — which will provide cool air in the summer and fall and heat during the winter.

The 1st floor and basement ceilings have been finished and painting will begin next week.  All of the rough-ins on the 1964 addition should be complete next week and ready for inspection.

Ceilings and drywall work is complete in the living room.

Fancoil units have been installed in the 1931 building.  This is taken in room 401 (old 4-South) — southwest corner.

Drywall will start next week in the dining room.

Read Full Post »

Passersby on R Street may be wondering what FIJI is doing with all the digging?  Is it a pool?  Nope.  Is it a ditch? Nope. Is it a moat? Nope (but I wish). It’s the primary reason this entire project started – fire sprinklers.  A dedicated water source is required for fire sprinklers and was installed this week. The fire sprinkler equipment will be located in the old bomb shelter.

The 1931 side of the house is nearing completion. The drywall crews moved to first floor and basement this week and painters have been to work on 2nd, 3rd and 4th floors.  The tile crew has finished the ‘old’ bathrooms.  The side of the house should be finished in the next few weeks.

The 1964 ‘new’ side – that’s another story. Third floor framing is currently on hold while the architect and structural engineer address existing structural concerns based on the original construction.

Next week ceilings will be installed on 2nd floor, new electrical service is being brought into the building and hopefully, the 3rd new framing will begin.

New windows have been installed in the 1964 addition.

Ceiling is up in the basement.  Fire code required the old exposed beams to be covered.

2nd ‘old’ bathroom — tile work is complete.

The entire house has new plumbing — this is take in the house mother’s living room — looking up to the plumbing for the 2nd old bathroom.

1931 building hallways have been painted.

Plumbing rough-ins have started on the 1964 addition — this is taken in the 2nd new bathroom — looking at the west wall (where the trash can use to sit). This will now be where the sinks are located.

Our trouble child – the 3rd floor of the 1964 addition — Now, I’m not a structural engineer – but it appears that the quite a bit of the roofing structure is resting on the interior walls.  This has caused challenges as the House Corporation changes the layout to the new suite style floor plan.  Stay-tuned on this one…

 

Read Full Post »

Walls going up in what was room 212 – will be 210.

As quickly as the walls in the 1964 addition came down, they are now going back up.  Once again, cinder block is being used on 2nd floor and hopefully 3rd. While more expensive to install, the lifetime maintenance of cinder block is significantly less than drywall. Because the 3rd floor was built with wood studs and plaster, our engineer wants to make sure the floor can hold cinder blocks before they are installed.  We will know this early next week.

As of the end of this week, there will no longer be any asbestos in the building.  While the Board knew the building contained asbestos when the project started, its extent was not known.  The asbestos removal is significantly over budget, by $30,000.

Drywall crews are working on the 1931 side of the building and should finish up in the near future. The tile installation crews will start next week in the 2nd and 3rd old bathrooms.

The finishes have been selected.  Walls will be painted a shade of beige, carpets are shades of browns, bathrooms will be tiled in shades of grey and beige, and new solid core wood doors will be installed.  PLEASE NOTE: the photograph’s DO NOT capture the correct colors.  They are posted so you can see the general look.  As an overall package, the colors, textures, tiles and other finishes are stunning.

A special thank you, again, to Jerry Solomon (Nebraska 1951) for his help in identifying photographs of Lambda Nu’s Innocents and athletes.  There are still a handful of unknown graduate Brother photos – please take a look and post a comment if you know the identity of the Brother.  The House Corporation is still collecting composites. Email the House Corporation if you have copies of composites not included in this collection.

Entrance into the new room 210 (approximate location of the old room 212). This was taken standing by where the supply closet was located.

2nd floor — taken in the southwest corner (was room 209).

2nd new bathroom has been stripped.  The old cast iron waste stacks have been taken down and will be replaced to accommodate a new floor layout.

Cinder blocks awaiting approval to be installed on 3rd floor (room 312).

The windows on 2nd and 3rd floor of the 1964 building have been removed. New windows will be installed in the next few weeks.

What’s left on the 3rd new bathroom.  If you look carefully, you can see the remains of an old window on the east wall.

Educational area of room 300.  Drywall is up and the mudding is underway.

Sleeping room 300a — located on the north side of the 1931 building. This will sleep three men.

The women’s restroom on 1st floor has been demoed. The grey wall in the back is part of the housemothers bedroom. The women’s restroom will change to an ADA complaint unisex restroom. What was the men’s restroom on 1st floor will now house the electrical and computer equipment.

Finishes — please note that the following photographs do not do the actual colors justice.  These are posted so you can get a general idea of what the finishes will look like. 

Paint — the walls are a light beige, metal trim will be painted a light brown and ceiling white.

Carpet — sample on the left will be used in the hallways, the grey on the right will be in the study rooms and browns will be in the bedrooms.

Doors — new doors will be solid core oak and stained.

Bathrooms — tiles will be a grey; counters will be the darker piece of grey and the partitions between toilets is the sample at the top of the photo.

Examples of lighting that may be used in the dining room, living room and bathrooms.  All study rooms, sleeping rooms and hallways will use recessed lighting.

Not pictured — the living room’s wood floors will be refurnished.

Read Full Post »

Cinder blocks from 2nd floor

The demo and asbestos crews have been busy – the first floor foyer, dining room, and hallway ceilings have been taken down.  The second and third floor walls have been taken down in the 1964 addition.  Demo has started in both bathrooms and should be finished next week.

Work continues in the 1931 building. Insulation is being installed on exterior and interior walls.  This will help with both energy efficiency and sound. Drywall and insulation has been installed on the fourth and third floors, including the third old bathroom.  The mason is building the new egress doors on second, third and fourth floors.

Next week the masons will start laying the walls on second and third floors of the 1964 building. Cinder blocks will be used which will help with longer term maintenance of the building (no more broken drywall).

If you would like to see the house in person, the House Corporation is hosting a breakfast next Thursday, May 26 at the chapter house.  The breakfast is from 7 to 9 a.m., with a short campaign update at 8 a.m. Please send an email if you plan to attend.  The cost if a suggested donation of $10.

Dining room, taken from the northwest corner looking towards the east.

The told tile has been removed in the kitchen. While the layout is not going to change, new appliances will be installed.

2nd new — taken from the northeast corner of what was the cleaning closet — looking towards the west.  The red wall on the right was room 206 and the red wall with the Husker N was room 210.  The cinder block wall in the middle of the photo is a load bearing wall and can not be removed. It was the south wall of room 210 and 211.

Hallway outside the balcony and 2nd new bathroom.  The ceiling has been removed.

2nd floor — taken from the southeast corner of room 206 looking to the west.  The purple wall was room 212.

Taken from the northwest corner of room 210 looking into room 211 and 212.

Standing in room 212, looking into the bedroom area of room 211 and 210 (the red wall).

Old side of the house — 2nd floor — this is where the window for the fire escape was located.  Code required a door be installed.

Southwest corner of 3rd floor (room 309) looking east.  The walls will be removed after the cinder blocks are stalled to hold up the roof.

Taken from room 310 – northwest corner looking into room 211 and 212.

A detail of the roof structure of the 1964 addition.

Demo in the third floor bathroom (3rd new)

3rd new bathroom — shower and toilet area.

Drywall in 3rd old bathroom looking at the area were the sinks will be installed. This was the area where the showers were located.

Interior insulation being installed in the new room 300 (approximate location is where the old room 301).

Drywall installed in the new room 301 (old 302). Standing in the educational/study area looking into the sleeping rooms.  These will both be private rooms.

Room 400.b — old 4South. This will be a bedroom for two brothers.

Goodbye 2nd new toilets — I think we’ve all cleaned these at one time or another.

Read Full Post »

Room 312, looking into 311 and 310

Finals are done, graduation is over and the undergraduate Phi Gams are out of the house – wrapping up another great year – now, let rest of the demo begin.

The demo crew started on the 3rd floor bringing down the walls, ceiling and stripping the bathroom.  At the same time, asbestos crews have removed the dining room and foyer ceiling along with the original floor tiles on 2nd floor. An unexpected surprise was to find that 75% of the floors on second and third floor had asbestos tiles under the carpet that has to be removed. Early next week the crews will swap with the flooring being removed on 3rd floor while the demo crew removes the walls and bathroom on 2nd floor.

Insulation, boxing and drywall continue on the 1931 building and should be wrapped up next few weeks.  All final finishes (doors, tiles, paint colors, carpet) have been identified and are on order to finish the old side of the house.

A request from the undergraduate brothers: The Rush Chairmen are busy starting the rush season – if you know of any good young men who plan to attend UNL this fall, please email their name and contact information.  If they decided to join Phi Gamma Delta, they will be living in one of the best fraternity houses on campus.

Taken from the southwest corner of 3rd floor (Room 309) looking into 308, 307 and 306.

3rd new hallway — looking for the nook that use to be outside room 311 towards the window.

The author of the blog had to purchase a new camera — a new feature — panorama’s — this is taken standing in the northwest corner of room 312.

Demo in the 3rd new bathroom — this is where the sinks use to be located.

A panorama of the demo in the 3rd new bathroom.

The new slide from what was room 307 — the undergraduate are going to love this!  (just kidding, will be used to shovel the 3rd floor remains to the dumpster, then be gone).

The House Corporation’s love affair with asbestos continues — the is is outside of the removal tent in the hallway outside the dining room.  Both the dining room ceiling and the tiles in the kitchen, hallway, break room, ice room and pantry contained asbestos.

Read Full Post »