The 2nd, 3rd and 4th floor demolition is complete. All interior walls, including both bathrooms, were hauled down R Street this week. The living room ceiling was taken down to allow for the installation of new electrical, plumbing, HVAC and fire sprinklers. The interiors of rooms B1 and B2 are cleared as well.
Next week includes finalizing the permits and the framers plan to start putting up the new walls. We also have the joy of dealing with asbestos removal in preparation of the HVAC guys starting their work.
Livingroom, looking to the north.
Livingroom, looking to the south
2nd floor — Standing in room 200 — looking to room 202 (green wall)
2nd Old bathroom — yup, this is a big project.
Standing in room 202, looking into room 203 (blue wall)
3rd floor — standing in room 300, looking into 301 (red wall) and 302 (tan wall)
3rd Old bathroom
Standing in room 302, looking into room 303 (green wall)
Standing in room 4north, looking into room 4south
Standing in 4south, looking into 4north
Basement — you really can’t tell much down here — but the ceiling panels have been pulled down and carpet removed.