June 9, 2011 by Eric

1st floor fire-rated window -- contains a wire mesh to prevent the window from breaking

When you start an extensive project – you expect there to be issues that will have to be addressed.  Sure, we knew there was asbestos that needed to go, fire sprinklers had to be installed even a few ADA issues that would need to be addressed – but, we did not know that we would have to install special windows on the fire escape. These fire-rated windows are specially designed to contain a fire inside the building. In addition to the new exit doors on each floor, these help ensure the safety of our Brothers in the event the building would need to be evacuated. Let’s just say, they cost a pretty penny – but, like the asbestos, it had to be done. 

New windows were installed in the 1964 addition on 2nd and 3rd floors. With these energy-efficient windows and all the new insulation, the chapter should save hundreds (if not thousands) of dollars each year in energy bills.  Last school year, the electricity bill ran between $1,000 to $1,400 a month and gas was $600 (without the boiler) to $3,000 (with boiler). It will be interesting to see how much these decrease.

Painting started on the 1931 side of the building this week.  All rooms are being painted the same color. To help keep the property looking nice for years to come, the house corporation is making several changes to the rental agreements – one of them being that undergraduate brothers will no longer be able to paint their room. 

The tile is down in both ‘old’ bathrooms and rough-in work continues in the ‘new’ bathrooms.

Rooms will be heated and air-conditioned using fan coil units, which arrived this week and will be installed on the 1931 side over the next few weeks.

New windows installed in the 1964 addition.  The 1st floor windows will go in next week.

A fire-rated window is ready to be installed in room 209 (was room 210).  Any window within 10′ of a fire escape must be fire-rated.

Painting has started in the 1931 building. This is room 300.A (north side of old room 300) and will be a sleeping room.
 
New windows in room 310 (was room 312).
 
Tile work is nearly done in the 3rd ‘old’ bath.
 
Rough-in’s continue in the ‘new’ bathrooms — this is 2nd new — standing at the door — looking to where the toilets use to be located.
Boxes of fancoils are stored in the dining room.
 
Bye-bye old door out of what was room B1 — it has now been bricked up. The stairs are scheduled to be removed when the new pad for the air conditioning equipment is poured.

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Related

Posted in 2nd new, 3rd old, basement, building codes, mechanical systems, plumbing, windows |

  • Donation infomation

    Read how to support the project by clicking on the “How to Donate” tab at the top of the screen.
  • Enter your email address to subscribe to this blog and receive notifications of new posts by email.

    Join 40 other subscribers
  • This Old FIJI House archives

    • October 2011 (1)
    • August 2011 (4)
    • July 2011 (4)
    • June 2011 (5)
    • May 2011 (4)
    • April 2011 (4)
    • March 2011 (4)
    • February 2011 (6)
  • Recent Posts

    • The project is complete
    • FIJI is ready for business
    • They day before the fraternity property returns

Blog at WordPress.com.

WPThemes.


Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Follow Following
    • This Old FIJI House
    • Join 40 other followers
    • Already have a WordPress.com account? Log in now.
    • This Old FIJI House
    • Customize
    • Follow Following
    • Sign up
    • Log in
    • Copy shortlink
    • Report this content
    • View post in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...
 

    %d bloggers like this: