Archive for the ‘plumbing’ Category

Refinished dining room tables

The painters have finished 2nd, 3rd, and 4th floors of the 1931 building. The camera is not doing the colors justice – the hallways and individual sleeping rooms are light beige with the study rooms a light brown.  Carpet should be installed next week.

Mechanical and electrical rough-ins continue in the 1964 addition.  Fire sprinklers are being installed in the entire building.

Lincoln Electric System buried the power line last week.  While it is nice to have this line concealed, the downside is the back lot took a beating.  Luckily, as they dug a trench from the pole to the back of the 1931 building, no surprises were found (such as a buried fuel tank).

A new stove and refrigerator has been ordered to replace the 1964 appliances.  The fraternity’s freezer is relatively new and will be reused.

The board was able to contract with Cornhusker State Industries to custom build dorm room furniture (will be installed in the completed rooms next week).  CSI also refinished the dining room tables and a few other wood pieces from the chapter house.  The dining room tables look brand new and are ready for another 50 years of FIJIs celebrating lunch and dinner together.

Room 200 — the study room and sleeping room has been painted.

Room 401 (old 4 south) — the hallway that leads to the main study room. The sleeping rooms  are off to the right. 

The bathroom on the 1931 building — 3rd floor — ready for final finishes.

Mechanical and electrical rough-ins. Photo is taken on 2nd floor — looking west into room 210 (old 212 and cleaning closet).

3rd floor bathroom, 1964 addition — plumbing rough-ins are installed.  Drywall should start soon.

Fire sprinkler rough-ins on the 3rd floor, 1964 addition.

The 1964 appliances have been removed and new ones are on order.  The kitchen layout will remain relatively the same.

The poor back lot has seen better days — LES dug a trench from the pole in the middle of the photo to the back of the 1931 building to install a new power main.

Read Full Post »

Passersby on R Street may be wondering what FIJI is doing with all the digging?  Is it a pool?  Nope.  Is it a ditch? Nope. Is it a moat? Nope (but I wish). It’s the primary reason this entire project started – fire sprinklers.  A dedicated water source is required for fire sprinklers and was installed this week. The fire sprinkler equipment will be located in the old bomb shelter.

The 1931 side of the house is nearing completion. The drywall crews moved to first floor and basement this week and painters have been to work on 2nd, 3rd and 4th floors.  The tile crew has finished the ‘old’ bathrooms.  The side of the house should be finished in the next few weeks.

The 1964 ‘new’ side – that’s another story. Third floor framing is currently on hold while the architect and structural engineer address existing structural concerns based on the original construction.

Next week ceilings will be installed on 2nd floor, new electrical service is being brought into the building and hopefully, the 3rd new framing will begin.

New windows have been installed in the 1964 addition.

Ceiling is up in the basement.  Fire code required the old exposed beams to be covered.

2nd ‘old’ bathroom — tile work is complete.

The entire house has new plumbing — this is take in the house mother’s living room — looking up to the plumbing for the 2nd old bathroom.

1931 building hallways have been painted.

Plumbing rough-ins have started on the 1964 addition — this is taken in the 2nd new bathroom — looking at the west wall (where the trash can use to sit). This will now be where the sinks are located.

Our trouble child – the 3rd floor of the 1964 addition — Now, I’m not a structural engineer – but it appears that the quite a bit of the roofing structure is resting on the interior walls.  This has caused challenges as the House Corporation changes the layout to the new suite style floor plan.  Stay-tuned on this one…

 

Read Full Post »

1st floor fire-rated window -- contains a wire mesh to prevent the window from breaking

When you start an extensive project – you expect there to be issues that will have to be addressed.  Sure, we knew there was asbestos that needed to go, fire sprinklers had to be installed even a few ADA issues that would need to be addressed – but, we did not know that we would have to install special windows on the fire escape. These fire-rated windows are specially designed to contain a fire inside the building. In addition to the new exit doors on each floor, these help ensure the safety of our Brothers in the event the building would need to be evacuated. Let’s just say, they cost a pretty penny – but, like the asbestos, it had to be done. 

New windows were installed in the 1964 addition on 2nd and 3rd floors. With these energy-efficient windows and all the new insulation, the chapter should save hundreds (if not thousands) of dollars each year in energy bills.  Last school year, the electricity bill ran between $1,000 to $1,400 a month and gas was $600 (without the boiler) to $3,000 (with boiler). It will be interesting to see how much these decrease.

Painting started on the 1931 side of the building this week.  All rooms are being painted the same color. To help keep the property looking nice for years to come, the house corporation is making several changes to the rental agreements – one of them being that undergraduate brothers will no longer be able to paint their room. 

The tile is down in both ‘old’ bathrooms and rough-in work continues in the ‘new’ bathrooms.

Rooms will be heated and air-conditioned using fan coil units, which arrived this week and will be installed on the 1931 side over the next few weeks.

New windows installed in the 1964 addition.  The 1st floor windows will go in next week.

A fire-rated window is ready to be installed in room 209 (was room 210).  Any window within 10′ of a fire escape must be fire-rated.

Painting has started in the 1931 building. This is room 300.A (north side of old room 300) and will be a sleeping room.
 
New windows in room 310 (was room 312).
 
Tile work is nearly done in the 3rd ‘old’ bath.
 
Rough-in’s continue in the ‘new’ bathrooms — this is 2nd new — standing at the door — looking to where the toilets use to be located.
Boxes of fancoils are stored in the dining room.
 
Bye-bye old door out of what was room B1 — it has now been bricked up. The stairs are scheduled to be removed when the new pad for the air conditioning equipment is poured.

Read Full Post »

One of the ‘fun’ aspects of a major remodel project is that everything has to be brought up to current building codes.  One of the code requirements we didn’t think about was the height of the wrought iron railing. This original 1931 railing goes from the basement to 4th floor – and is not high enough to meet current code. Thankfully, the City of Lincoln recognizing that the primary user of this railing is young men in the prime of their life, we received special permission to keep the existing railing.

Unfortunately, we are not as lucky in a few other areas.  Due to the various bathroom remodels over the past 80 plus years – some of the bathroom floor joist had significant notches cut in them to accommodate plumbing.  While a new 2 x 12 has been placed next to the old joist, the city wants our engineers to review to ensure they are structurally sound.  We’re also waiting to see if we will have to install the special fire rated windows next to the fire escape…stay tuned.

If we are able to resolve these issues – insulation and drywall should start next week. 

The plumbing rough-ins for 3rd old bathroom sinks.  The sinks will be on the south wall — where the showers were located.

The rough in for the new washer/dryer on second floor.  This is in the hallway between the old and new side of the building.

the floor is being built up in what was the bedroom area of B1.  This will be a new study/computer room.  The west door that leads to the back lot will be removed and the stairwell filled in as the electical service is updated to the building.

Read Full Post »