August 4, 2011 by Eric

Carpet, doors, and trim – the chapter house is starting to look like a home.  The next two weeks are going to be a flurry of activity to finish by August 17.  This week carpet is being installed in the hallways of the 1931 building and in the rooms of the 1964 addition.   The living room and housemother’s floors are being sanded and finished.

New solid core doors are being installed throughout the house.   A master-key system will be installed that will allow the house corporation to have a single key that will open all doors.  Each student’s key will unlock their study and assigned sleeping room door.

Next week’s highlights include firing up the air conditioner for the first time, installing the wireless internet system and rest of the finishes. FIJI is hosting all the UNL fraternity and sorority house corporations next week during the greek house tour.

If you haven’t done so already — mark your calendar and plan to attend Pig Dinner on Friday, October 7, 2011.  The chapter house dedication ceremony will take place on Friday at 4.30 p.m. with the 106th Norris Pig Dinner starting at 7. This year’s keynote address will be by the Honorable J. Robert Kerrey (Nebraska 1965), Former United States Senator and Governor of Nebraska.

Painting starts in the kitchen.  The kitchen will get a new stove and refrigerator.

The old ice room will house a new residential refrigerator, microwave and new ice machine.  Late plates and extra food will be stored in this room for guys to have access to in the evening.  The kitchen will remained locked when the cook is not present.

The 1964 stairwell has been painted and new railing installed.  Code requires new railings in both the 1964 and 1931 stairwells.

New hallway carpet in the 3rd floor of the 1931 building.

New doors have been installed.

The 3rd floor bathroom in the 1964 addition is ready for its final finishes.

New main electrical service panel — this feeds each of the subpanels on each floor.

All of the heating and cooling plumbing was redone.  The boiler room ceiling is almost fully covered in insulted pipes.

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Related

Posted in 3rd new, 3rd old, basement, building codes, carpet, insulation, kitchen, mechanical systems, Uncategorized |

  • Donation infomation

    Read how to support the project by clicking on the “How to Donate” tab at the top of the screen.
  • Enter your email address to subscribe to this blog and receive notifications of new posts by email.

    Join 40 other subscribers
  • This Old FIJI House archives

    • October 2011 (1)
    • August 2011 (4)
    • July 2011 (4)
    • June 2011 (5)
    • May 2011 (4)
    • April 2011 (4)
    • March 2011 (4)
    • February 2011 (6)
  • Recent Posts

    • The project is complete
    • FIJI is ready for business
    • They day before the fraternity property returns

Blog at WordPress.com.

WPThemes.


Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Follow Following
    • This Old FIJI House
    • Join 40 other followers
    • Already have a WordPress.com account? Log in now.
    • This Old FIJI House
    • Customize
    • Follow Following
    • Sign up
    • Log in
    • Copy shortlink
    • Report this content
    • View post in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...
 

    %d bloggers like this: