Feeds:
Posts
Comments

Archive for the ‘fire sprinklers’ Category

The fire sprinkler main is open

Lots of progress this week – with dorm room furniture scheduled to be delivered on Friday, July 15 for the 1931 side.  The crews have been busy installing the fire sprinkler system (the item that started this entire project), HVAC equipment, carpet and paint.  Based on all known information at this point, the project is scheduled to be ready for the undergraduates to move in on August 15.

Inspections were approved to start finish work on the 1964 addition.  Drywall has been hung in the dining room, foyer, 2nd floor ceiling and 3rd floor.  Work continues on the bathroom.

The entire building will now enjoy central air.  The cooling equipment sits in the corner of the parking lot – where the ‘new’ and ‘old’ houses meet.  While this location is not ideal, it is the best solution that could be developed given the multiple factors that needed to be considered (including distance from the mechanical room and costs).  We were able to continue to use the boiler that was installed in 1997 for heat.

An individual ‘make-up’ air unit was installed for the kitchen.  This will provide both additional heat and air conditioning for this specific area of the chapter house.  The guys are going to have some cool cooks.   In addition, a new stove and refrigerator are on order for the kitchen.

The new AC has been installed on its pad.  While not ideal, this was the best of many not-so-good options.

Make-up air unit for the kitchen.  This will provide additional heating and cooling.

The living room has been primed with tinted primer.

The dining room has had drywall hung.

The housemother’s bedroom. Due to changes to the women’s restroom (will now be an ADA complain unisex restroom), the housemother’s bedroom gained much-needed, and I’m sure apprecaited, square footage.

Room 200 (formerly 200 and 201) carpet has been installed.  The camera continues not to do the actual colors justice.

Room 302 (formerly 303).

The 1964 addition has a little ways to go — this is taken in the study room of the new 309 (formerly 310 and 311), standing on the south wall — looking to the north.

The poor back lot took a beating and is scheduled to be paved next week.  The cement pad at the top of the photo is the location of the new transformer that will be installed next week as well.

Read Full Post »

Refinished dining room tables

The painters have finished 2nd, 3rd, and 4th floors of the 1931 building. The camera is not doing the colors justice – the hallways and individual sleeping rooms are light beige with the study rooms a light brown.  Carpet should be installed next week.

Mechanical and electrical rough-ins continue in the 1964 addition.  Fire sprinklers are being installed in the entire building.

Lincoln Electric System buried the power line last week.  While it is nice to have this line concealed, the downside is the back lot took a beating.  Luckily, as they dug a trench from the pole to the back of the 1931 building, no surprises were found (such as a buried fuel tank).

A new stove and refrigerator has been ordered to replace the 1964 appliances.  The fraternity’s freezer is relatively new and will be reused.

The board was able to contract with Cornhusker State Industries to custom build dorm room furniture (will be installed in the completed rooms next week).  CSI also refinished the dining room tables and a few other wood pieces from the chapter house.  The dining room tables look brand new and are ready for another 50 years of FIJIs celebrating lunch and dinner together.

Room 200 — the study room and sleeping room has been painted.

Room 401 (old 4 south) — the hallway that leads to the main study room. The sleeping rooms  are off to the right. 

The bathroom on the 1931 building — 3rd floor — ready for final finishes.

Mechanical and electrical rough-ins. Photo is taken on 2nd floor — looking west into room 210 (old 212 and cleaning closet).

3rd floor bathroom, 1964 addition — plumbing rough-ins are installed.  Drywall should start soon.

Fire sprinkler rough-ins on the 3rd floor, 1964 addition.

The 1964 appliances have been removed and new ones are on order.  The kitchen layout will remain relatively the same.

The poor back lot has seen better days — LES dug a trench from the pole in the middle of the photo to the back of the 1931 building to install a new power main.

Read Full Post »

Carpet installed in room 300.A

The 1931 building final finishes continue – carpeting is being installed in sleeping rooms, the living room and basement drywall should be finished this week and the painter is scheduled to return next.  The plan is to refinish the 1st floor original hardwood floors after the painter is done.

As noted last week, the 3rd floor and roof of the 1964 addition did not meet current building codes.  A plan has been developed and approved to  install additional support beams – framing should begin next week.

Ceilings will be installed next week in the dining room and 2nd floor of the 1964 addition next week.

The project is on target for an August 15 finish date.

2nd ‘old’ bathroom — standing in the southwest corner (where the showers use to be) looking to the northeast.  Each bathroom will have two private shower stalls.

Drywall work continues in the living room and should finish this week.  Insulation was installed in the exterior walls.  The cove above the 2nd set of windows conceal the heating and air conditioning systems for rooms 200 and 201.

Workers install the ceiling system in the dining room.  The drywall can not be screwed directly to beams as that alters the structural integrity — so instead they screw the drywall to these channels — which also helps reduce sound transmitting from floor to floor.

The new fire sprinkler shut-off valve.

Doors will be installed to the 1964 addition fire escape. In addition, any window within 10 feet of the fire escape must be a fire-rated window. These non-operable windows have a wire mesh imbedded in the glass.  In the event of a fire, this would delay the window from breaking under — thus allowing the residents to safely exit the building using the fire escape.

Read Full Post »

Passersby on R Street may be wondering what FIJI is doing with all the digging?  Is it a pool?  Nope.  Is it a ditch? Nope. Is it a moat? Nope (but I wish). It’s the primary reason this entire project started – fire sprinklers.  A dedicated water source is required for fire sprinklers and was installed this week. The fire sprinkler equipment will be located in the old bomb shelter.

The 1931 side of the house is nearing completion. The drywall crews moved to first floor and basement this week and painters have been to work on 2nd, 3rd and 4th floors.  The tile crew has finished the ‘old’ bathrooms.  The side of the house should be finished in the next few weeks.

The 1964 ‘new’ side – that’s another story. Third floor framing is currently on hold while the architect and structural engineer address existing structural concerns based on the original construction.

Next week ceilings will be installed on 2nd floor, new electrical service is being brought into the building and hopefully, the 3rd new framing will begin.

New windows have been installed in the 1964 addition.

Ceiling is up in the basement.  Fire code required the old exposed beams to be covered.

2nd ‘old’ bathroom — tile work is complete.

The entire house has new plumbing — this is take in the house mother’s living room — looking up to the plumbing for the 2nd old bathroom.

1931 building hallways have been painted.

Plumbing rough-ins have started on the 1964 addition — this is taken in the 2nd new bathroom — looking at the west wall (where the trash can use to sit). This will now be where the sinks are located.

Our trouble child – the 3rd floor of the 1964 addition — Now, I’m not a structural engineer – but it appears that the quite a bit of the roofing structure is resting on the interior walls.  This has caused challenges as the House Corporation changes the layout to the new suite style floor plan.  Stay-tuned on this one…

 

Read Full Post »

New windows on the old side of the house.

Dramatic changes this week – new windows were installed on the north, east and west side of the 1931 building.  The new windows will significantly improve the energy efficiency of the chapter house.  The existing windows were installed decades ago and had outlived their useful life.  Many of old window vinyl tracks had degraded to the point where it was a battle to keep the windows closed.  New windows are being installed in the entire building – from the 4th floor to the basement.  

The windows on the south side have not been installed. Fire code requires that any window within 10 feet of a fire escape be fire-rated.  These windows cost nearly four times of what the regular windows cost.  And, because it is an old building, everything is a custom size.

In addition to fire-rated windows, openings were cut into the 2nd, 3rd, and 4th floor to accommodate exit doors. Current fire code requires doors be used instead of the existing windows.

Fire sprinkler rough-ins have been installed.

Sleeping room furniture will be ordered this week.  The order includes 28 extra long twin bunk beds, 6 single beds, 3 lofted singled beds, 30 wardrobes, 30 dressers, 65 mattresses and 25 desks.  The items are built locally and will be delivered and installed in August.

Next week includes inspections of rough in electrical, mechanical and plumbing; insulating; and, starting drywall.

New windows on the east side of the building — next door to ATO.

West side of the house — new windows (and the old windows in the red dumpster).

South side of the building (like the bathroom?) — all of these windows will have to be fire-rated. On the left side of the photo — opening have been cut into the walls to accommodate new exit doors.

New windows in B2.  This will be one of the few three men rooms.

FIJI graffiti – it has been interesting what has been ‘found’ under the walls – including a “More PhiGam, Less Self” bronze plaque. This is in the area formerly known as B1.

2nd floor — will be room 200, looking south into the future room 201. 

New layout for the 2nd old bathroom — the metal walls will house individual shower stalls. The stools will be to the left.  This is taken standing on the south wall (where the sinks will be), looking north (the stairwell is behind the wall).

Standing in the educational area of the future room 300, looking north.

Laundry will move from the basement to 2nd and 3rd floors.  This is where the old sauna was located and will house a washer and dryer.

 The item that started this entire process — rough ins for the fire sprinkler (red pipe).  The Board of Regents has required all student housing (including greek housing) be sprinkled by 2017 — Phi Gamma Delta will be well ahead of the game on this issue.

Read Full Post »